BEHIND THE SCENES: MARCH CONSTRUCTION UPDATE VIDEO
Marching into the Lenten Season
In the month of February, our little town in Kansas shivered through the cold weather and winter storms that swept through much of the continental United States. Sub-zero temperatures stalled construction for over a week while wintery conditions have created difficulties in the precision of the construction required for this project.
But with every time of setback or difficulty, there also comes a time of rejoicing and exaltation. Providence allows a mirroring of the feast of Easter with the rising visible progress of the ascending vertical steel beams.
Through this month of March, the eastern vertical steel work will move into the next phase of framing the east wall. The nave and transept slab decks will be poured, and we will also see an access road being prepared for the incoming masonry contractors, getting the commotion ramped up again and ready for Spring at the Immaculata Church Project.